Orbach Library First Floor Reflooring Project: Service Impacts

We are reflooring the first floor of Orbach Library. To keep as much of the building as functional as possible, flooring and carpeting replacement will happen in phases over the rest of summer. 

The first floor will remain open throughout the project, along with all upper floors. However, because work is being done in phases, specific first-floor areas, services, computing stations, and specialized labs will close or be disrupted as work moves through each area of the first floor. Pease note, construction crews will be working during morning and afternoon hours, Monday through Friday.

Services Disruption Timeline for Orbach Library
DatesAffected ServiceImpact Details
Mon 8/17 – Thu 8/20Laptop KiosksService unavailable
Tue 8/25Poster PrintingClosed
Thu 8/27 – Fri 9/4IT BearHelp / Library Info DeskClosed
Tue 9/8 – Fri 9/11Patron Desktop ComputersService unavailable
Mon 9/14Creat'R Lab MakerspaceClosed
Mon 9/14 – Wed 9/23WEPA PrintersService unavailable
Tue 9/15 – Wed 9/23Specialized LabsClosed: Robotics, Multimedia, and STAR Lab
Building Access & Safety Reminders
  • Restricted areas: Active work zones on the first floor will be closed off with barriers and mobile sign stands. For everyone's safety, students, faculty, and patrons must not enter any closed off areas.
  • Service/freight elevator access: On some days, the service/freight elevator will not be accessible on the first floor. The main elevator and stairwell will remain open and accessible throughout the project.
  • Noise: Expect periodic construction noise on the first floor and in nearby areas.

Thank you for your patience as we improve our facilities.